Question : A and B together can complete a given work in 10 days. C can complete the same work alone in 15 days. In how many days can they complete the work, if all three work together?
Option 1: 8 days
Option 2: 5 days
Option 3: 6 days
Option 4: 10 days
Correct Answer: 6 days
Solution :
1 day's work of A and B =
1 day's work of C =
1 day's work of A, B and C together =
Thus, the work is completed in 6 days.