Question : 10 men can do work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:

Option 1: 10

Option 2: 8

Option 3: 6

Option 4: 12


Team Careers360 14th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: 10


Solution : Given: 10 men can do a work in 25 days. After 12 days of work, 3 more men were engaged to finish the work.
Here, $M_1=10,M_2=10+3=13,D_1=25-12=13$
We know, $M_1D_1= M_2D_2$
⇒ 10 × 13 = 13 × D 2
$\therefore$ D 2 = 10 days
Hence, the correct answer is 10.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books