Question : 12 men can complete a work in 6 days working 4 hours per day. If 4 men work 8 hours per day, then in how many days the same work will be completed?

Option 1: 8 days

Option 2: 6 days

Option 3: 9 days

Option 4: 10 days


Team Careers360 4th Jan, 2024
Answer (1)
Team Careers360 9th Jan, 2024

Correct Answer: 9 days


Solution : Time taken by 12 men working 4 hours daily = 6 days
$\therefore$ Volume of work = 12 × 6 × 4 = 288
Let the time taken by 4 men working 8 hours daily be $x$ days.
According to the question,
$x × 8 × 4 = 288$
$\therefore x= \frac{288}{32}= 9$
Hence, the correct answer is 9 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books