Question : 12 men can complete a work in 6 days working 4 hours per day. If 4 men work 8 hours per day, then in how many days the same work will be completed?
Option 1: 8 days
Option 2: 6 days
Option 3: 9 days
Option 4: 10 days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 9 days
Solution : Time taken by 12 men working 4 hours daily = 6 days $\therefore$ Volume of work = 12 × 6 × 4 = 288 Let the time taken by 4 men working 8 hours daily be $x$ days. According to the question, $x × 8 × 4 = 288$ $\therefore x= \frac{288}{32}= 9$ Hence, the correct answer is 9 days.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : If 20 men can complete a piece of work in 18 days working 5 hours per day, in how many days can 25 men complete it, working 6 hours per day?
Question : Working 12 hours per day, Raj can complete a work in 12 days. How many hours per day he should work to finish the same work in 9 days?
Question : 42 boys can complete a piece of work in 20 days working 8 hours per day. In how many days can 14 boys complete the same work, each boy working 12 hours per day?
Question : Working 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work to finish the work in 18 days?
Question : Suresh alone can do work in 10 days working 1 hour a day. Balu alone can do the same work in 2 days working 5 hours a day. How many hours do they need to work together in a day to complete the same work in 10 days?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile