Question : 14 workers working 16 hours per day can demolish a building in 81 days. In how many days 18 workers working 24 hours per day can demolish the same building?

Option 1: 54 days

Option 2: 42 days

Option 3: 70 days

Option 4: 30 days


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 42 days


Solution : Given that 14 workers working 16 hours per day can demolish a building in 81 days, the total man-hours required to demolish the building is,
Total man-hours = 14 × 16 × 81
If 18 workers are working 24 hours per day, the number of days they would take to demolish the same building is,
Number of days = $\frac{14 \times 16 \times 81}{18 \times 24}$ = 42
Hence, the correct answer is 42 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books