Question : 15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:
Option 1: $5\frac{5}{11}$
Option 2: $4\frac{3}{11}$
Option 3: $7\frac{2}{11}$
Option 4: $6\frac{4}{11}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
Correct Answer: $5\frac{5}{11}$
Solution :
Time taken by 15 men to complete the work = 10 days
⇒ Part of work done by 15 men in a day = $\frac{1}{10}$
Time taken by 15 women to complete the work = 12 days
⇒ Part of work done by 15 women in a day = $\frac{1}{12}$
Let time taken by (15 men + 15 women) to complete the work = $x$ days
⇒ Part of work done by (15 men + 15 women) in a day = $\frac{1}{x}$
⇒ $\frac{1}{10}$ + $\frac{1}{12}$ = $\frac{1}{x}$
⇒ $\frac{1}{x}$ = $\frac{11}{60}$
Time taken by (15 men + 15 women) to complete the work = $\frac{60}{11}$ = $5\frac{5}{11}$days
Hence, the correct answer is $5 \frac{5}{11}$.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.