Question : 15 men take 20 days to complete a job, working 8 hours a day. The number of hours a day that 20 men should take to complete the job in 12 days.

Option 1: 5 hours

Option 2: 10 hours

Option 3: 15 hours

Option 4: 18 hours


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 10 hours


Solution : Given that 15 men can complete a job in 20 days, working 8 hours a day.
$⇒15 \times 20 \times 8 \times r = 1$
Where $r$ is the rate of work.
The number of hours a day that 20 men should take to complete the job in 12 days. Let's assume that each man works $h$ hours per day.
$⇒20 \times 12 \times h \times r = 1$
Equating the two expressions for $r$,
$⇒15 \times 20 \times 8 \times r = 20 \times 12 \times h \times r$
$⇒h = \frac{15 \times 20 \times 8}{20 \times 12}=10$
Therefore, each man needs to work $10$ hours per day.
Hence, the correct answer is 10 hours.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books