Question : 16 boys or 12 women can do a piece of work in 28 days. In how many days will the same work be done by 4 boys and 4 women, if they all work together?

Option 1: 36 days

Option 2: 48 days

Option 3: 44 days

Option 4: 40 days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 48 days


Solution : Let the total work to be done is 1 unit.
16 boys or 12 women can do the work in = 28 days
1 boy's 1 day's of work = $\frac{1}{(16 \times 28)} = \frac{1}{448}$
And, 1 woman's 1 day's work = $\frac{1}{(12 \times 28)} = \frac{1}{336}$
The work done by 4 boys and 4 women in one day
= $4 \times (\frac{1}{448}) + 4 \times (\frac{1}{336})$
=$\frac{1}{112}+\frac{1}{84}$
= $\frac{1}{48}$
$\therefore$ The required number of days for 4 boys and 4 women to complete the work together is 48 days.
Hence, the correct answer is 48 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books