Question : 18 men can do a piece of work in 20 days. After working for 8 days, they get a notice to complete the work 4 days earlier than originally scheduled. How many more men will be required to be hired to complete the work as per the new schedule?

Option 1: 9

Option 2: 12

Option 3: 8

Option 4: 15


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 9


Solution : 18 men can do a piece of work in = 20 days
After working for 8 days, they get a notice to complete the work 4 days earlier than originally scheduled
The total work = 18 × 20 = 360 units
Work for 8 days then the work completed in 8 days = 18 Men × 8 Days = 144 units
The work done in 8 days by 18 men = 144 units
The remaining work = 360 – 144 = 216
The remaining days is = 20– 4 – 8 = 20 – 12 = 8 days
The more men required to complete the work in 8 days are $x$.
⇒ 216 = (18 + $x$) × 8
⇒ 18 + $x$ = 27
⇒ $x$ = 27 – 18 = 9
$\therefore$ 9 more men are required to complete the work as per the new schedule.
Hence, the correct answer is 9.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books