Question : 22 boys, working together, can complete a work in 10 days, whereas 25 boys and 12 girls take 8 days to complete the same work. In how many days can only 6 girls, working together, complete the same work?

Option 1: 170

Option 2: 177

Option 3: 175

Option 4: 176


Team Careers360 10th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 176


Solution : Number of days taken by 22 boys to complete a work = 10 days
Number of days taken by 25 boys and 12 girls to complete the same work = 8 days
Let the efficiency of a boy = B
The efficiency of a girl = G
Total work = 22 × 10 × B = (25 × B + 12 × G) × 8
⇒ 20 × B = 96 × G
⇒ $\frac{\text{B}}{\text{G}} = \frac{24}{5}$
Let B = 24k and G = 5k
So total work = 22 × 10 × 24k
The efficiency of a girl = 5k
So, the required days = $\frac{22 × 10 × 24\text{k}}{5\text{k} × 6}$ = 22 × 8 = 176 days
Hence, the correct answer is 176 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books