Question : 24 men can complete a work in 15 days. How many men are needed to complete the same work in 10 days?

Option 1: 16

Option 2: 20

Option 3: 36

Option 4: 25


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 36


Solution : We know,
$M_1D_1= M_2D_2$
Where $M_1$ and $M_2$ are persons and $D_1$ and $D_2$ are days.
So, $24×15=M_2×10$
$\therefore M_2=\frac{24×15}{10}=36$
Hence, the correct answer is 36.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books