2 Views

Question : 24 men can complete a work in 15 days. How many men are needed to complete the same work in 10 days?

Option 1: 16

Option 2: 20

Option 3: 36

Option 4: 25


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 36


Solution : We know,
$M_1D_1= M_2D_2$
Where $M_1$ and $M_2$ are persons and $D_1$ and $D_2$ are days.
So, $24×15=M_2×10$
$\therefore M_2=\frac{24×15}{10}=36$
Hence, the correct answer is 36.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books