Question : 24 women and 9 men can complete a certain piece of work in 18 days. Each woman takes twice the amount of time taken by a man to finish the work. In how many days can only 9 men finish the same work?

Option 1: 42

Option 2: 35

Option 3: 39

Option 4: 48


Team Careers360 3rd Jan, 2024
Answer (1)
Team Careers360 6th Jan, 2024

Correct Answer: 42


Solution : 24 Women + 9 Men = 18 days
Each woman takes twice the amount of time taken by a man to finish the work.
So, 1 man = 2 woman
⇒ 9 men = 9 × 2 = 18 women
So, 24 + 18 = 42 women complete the work in 18 days.
We know, $W_1D_1= W_2D_2$, where $W_1,W_2$ are number of women, $D_1,D_2$ are number of days
⇒ $42×18=18×D_2$
$\therefore D_2=42$
Hence, the correct answer is 42 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books