Question : 4 men’s work is equal to 6 women’s work and 4 women’s work is equal to 6 boy's work. A boy can finish the work in 60 days. In how many days can the work be finished by a man and a woman together?

Option 1: 16

Option 2: 24

Option 3: 20

Option 4: 12


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 16


Solution : Let the efficiency of a woman, a man, and a boy be w, m, and b, respectively.
According to the question,
4m = 6w and 4w = 6b
Let b = 4 units per day, then w = 6 units per day, and m = 9 units per day.
Now, total work = 4 × 60 = 240 units
One day work of 1 man and 1 woman = 9 + 6 = 15 units
So, the time taken by 1 man and 1 woman to complete the work = $\frac{240}{15}=16$ days
Hence, the correct answer is 16.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books