Question : 4 men’s work is equal to 6 women’s work and 4 women’s work is equal to 6 boy's work. A boy can finish the work in 60 days. In how many days can the work be finished by a man and a woman together?

Option 1: 16

Option 2: 24

Option 3: 20

Option 4: 12


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 16


Solution : Let the efficiency of a woman, a man, and a boy be w, m, and b, respectively.
According to the question,
4m = 6w and 4w = 6b
Let b = 4 units per day, then w = 6 units per day, and m = 9 units per day.
Now, total work = 4 × 60 = 240 units
One day work of 1 man and 1 woman = 9 + 6 = 15 units
So, the time taken by 1 man and 1 woman to complete the work = $\frac{240}{15}=16$ days
Hence, the correct answer is 16.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books