Question : 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will it now take to complete the remaining work?

Option 1: 6

Option 2: 8

Option 3: 10

Option 4: 12


Team Careers360 5th Jan, 2024
Answer (1)
Team Careers360 11th Jan, 2024

Correct Answer: 8


Solution : Total work = 40 × 18 = 720 units
Work done for 8 days by 40 men = 320 units
$\therefore$ Remaining work = 720 – 320 = 400 units
400 units of work are done by 50 men.
Thus, the remaining work is completed in $\frac{400}{50}$ = 8 days
Hence, the correct answer is 8.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books