Question : 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will it now take to complete the remaining work?

Option 1: 6

Option 2: 8

Option 3: 10

Option 4: 12


Team Careers360 5th Jan, 2024
Answer (1)
Team Careers360 11th Jan, 2024

Correct Answer: 8


Solution : Total work = 40 × 18 = 720 units
Work done for 8 days by 40 men = 320 units
$\therefore$ Remaining work = 720 – 320 = 400 units
400 units of work are done by 50 men.
Thus, the remaining work is completed in $\frac{400}{50}$ = 8 days
Hence, the correct answer is 8.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books