Question : 42 boys can complete a piece of work in 20 days working 8 hours per day. In how many days can 14 boys complete the same work, each boy working 12 hours per day?

Option 1: 39 days

Option 2: 40 days

Option 3: 41 days

Option 4: 42 days


Team Careers360 25th Jan, 2024
Answer (1)
Team Careers360 27th Jan, 2024

Correct Answer: 40 days


Solution : Let the number of days be $D$ for 14 boys working 12 hours per day.
Use the formula: $M_1D_1H_1= M_2D_2H_2$
Where $M_1$ and $M_2$ are persons, $D_1$ and $D_2$ are days and $H_1, H_2$ are hours per day.
⇒ 42 × 20 × 8 = 14 × D × 12
⇒ $D$ = 40
Hence, the correct answer is 40 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books