Question : 63 men can complete a work in 30 days. In how many days 21 men will do the same work?
Option 1: 70 days
Option 2: 85 days
Option 3: 90 days
Option 4: 88 days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 90 days
Solution : Here $M_1=63,M_2=21,$ and $D_1=30$ We know, $M_1 ×D_1=M_2 ×D_2$ $⇒63 × 30 = 21 ×D_2$ $\therefore D_2=90$ Hence, the correct answer is 90 days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : 35 men can complete a work in 15 days. 15 women can complete the same work in 35 days. In how many days 9 men and 16 women can complete the work?
Question : 9 boys and 12 men can complete a work in 24 days. Each boy takes thrice the time taken by a man to complete the work. In how many days will 15 men complete the same work?
Question : 12 men can complete a work in 6 days working 4 hours per day. If 4 men work 8 hours per day, then in how many days the same work will be completed?
Question : If 10 men can do work in 10 days, then in how much time will 2 men do the same work?
Question : 5 men can complete a work in 12 days, and 6 women can complete the same work in 20 days. In how many days can 1 man and 1 woman together complete this work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile