Question : 8 men can complete a task in 45 days. 8 women can complete the same task in 18 days. In how many days will 5 men and 8 women, together, complete the same task?
Option 1: $13 \frac{1}{5}$
Option 2: $12 \frac{4}{5}$
Option 3: $14 \frac{2}{5}$
Option 4: $15 \frac{3}{5}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
Correct Answer: $14 \frac{2}{5}$
Solution :
First, use $M_1D_1= M_2D_2$ Where $M_1$ and $M_2$ are men and women and $D1$ and $D_2$ are days.
$8M\times 45 = 8 W\times 18$
⇒ $5M=2W$
So, $5M + 8W=2W + 8W = 10W$
Now,
$8\times 18 = 10\times D_3$
⇒ $D_3 = \frac{8\times 18}{10} =\frac{72}{5}=14 \frac{2}{5}$ days.
Hence, the correct answer is $14 \frac{2}{5}$.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.