Question : 9 boys and 12 men can complete a work in 24 days. Each boy takes thrice the time taken by a man to complete the work. In how many days will 15 men complete the same work?
Option 1: 26 days
Option 2: 30 days
Option 3: 24 days
Option 4: 22 days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 24 days
Solution : (9 boys + 12 men) complete the work in 24 days. The ratio of time taken by a boy and time taken by a man = 3 : 1 i.e., 3 boys are equivalent to 1 man. $\therefore$ 9 boys are equivalent to 3 men. So, (3 men + 12 men) are equivalent to 15 men So, 15 men complete the work in 24 days. Hence, the correct answer is 24 days.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : 24 women and 9 men can complete a certain piece of work in 18 days. Each woman takes twice the amount of time taken by a man to finish the work. In how many days can only 9 men finish the same work?
Question : 35 men can complete a work in 15 days. 15 women can complete the same work in 35 days. In how many days 9 men and 16 women can complete the work?
Question : A and B together complete a work in 20 days, B and C together complete the same work in 30 days, and C and A together complete the same work in 24 days. In how many days A, B, and C together can complete the same work?
Question : A can do a work alone in 60 days and B can do the same work alone in 33.33% less time taken by A. Find the time taken by B to complete the work alone.
Question : 42 boys can complete a piece of work in 20 days working 8 hours per day. In how many days can 14 boys complete the same work, each boy working 12 hours per day?