Question : A alone can complete a work in 18 days and B alone in 15 days. B alone worked at it for 10 days and then left the work. In how many more days, will A alone complete the remaining work?

Option 1: $5$ days

Option 2: $5\frac{1}{2}$ days

Option 3: $6$ days

Option 4: $8$ days


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: $6$ days


Solution : Time taken by A to complete the work = 18 days
Time taken by B to complete the work = 15 days
Work done by A in a day = $\frac{1}{18}$
Work done by B in a day = $\frac{1}{15}$
Work done by B in 10 days = $\frac{10}{15}$
Work left = $1-\frac{10}{15}=\frac{1}{3}$
So, time taken by A to complete the remaining work = $\frac{\text{Work left}}{\text{work done in a day}} = \frac{\frac{1}3}{\frac{1}{18}}=6$
Hence, the correct answer is 6 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books