Solution : Let the total work be 50 units (LCM of 25 and 50).
Now, the efficiency of A = $\frac{50}{25}$ = 2
and the efficiency of B = $\frac{50}{50}$ = 1
So, A and B together in 1 day can do (2 + 1) = 3 units of work
$\therefore$ In 9 days they will do (3 × 9) = 27 units of work.
So, the required percentage = $\frac{27}{50}$ × 100 = 54%
Hence, the correct answer is 54%.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books