Question : A alone can do a work in 4 days, which B alone can do in 6 days. In how many days they together can do it?
Option 1: $\frac{7}{12}$
Option 2: $\frac{12}{7}$
Option 3: $\frac{12}{5}$
Option 4: $\frac{5}{12}$
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{12}{5}$
Solution : Given: A alone can do a work in 4 days. B alone can do it in 6 days. They together in 1 day can do ($\frac{1}{4}+\frac{1}{6}$) part of the work $=\frac{6+4}{24}=\frac{10}{24}=\frac{5}{12}$ part of the work So, they together can complete the work in $\frac{12}{5}$ days. Hence, the correct answer is $\frac{12}{5}$.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : A can do a work in 6 days, which B alone can do in 8 days. In how many days they together can do it?
Question : Avi alone can do a piece of work in 60 days while Prakash alone can do it in 80 days. In how many days will they finish it together?
Question : $P_1$ and $P_2$ can do a piece of work together in 14 days, $P_2$ and $P_3$ can do the same work together in 21 days, while $P_3$ and $P_1$ can do it together in 42 days. How much work can all the 3 together do in 12 days?
Question : A alone can do $\frac{1}{4}$th part of the work in 12 days. B alone can do $\frac{1}{5}$th part of the work in 4 days. In how many days can A and B together can do the same work?
Question : A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. In how many days will they complete $\frac{3}{4}$th of the total work?