Question : A alone can finish a work in 15 days. A works only for the first two days and the last two days. The rest work is done by B and the work is completed in 20 days. In how many days A and B together can finish the work?
Option 1: $\frac{90}{8}$
Option 2: $\frac{80}{7}$
Option 3: $\frac{80}{9}$
Option 4: $\frac{70}{8}$
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: $\frac{80}{9}$
Solution : Time taken by A alone to do the work = 15 Work done by A alone in a day = $\frac{1}{15}$ Work done by A in the first and last two days = $\frac{4}{15}$ Work done by B in 16 days = 1 – $\frac{4}{15}$ = $\frac{11}{15}$ Work done by B alone in a day = $\frac{11}{15×16}$ = $\frac{11}{240}$ Work done by A and B together in a day = $\frac{1}{15}$+$\frac{11}{240}$ = $\frac{27}{240}$ = $\frac{9}{80}$ $\therefore$ Time taken by A and B together to do the work = $\frac{80}{9}$ days Hence, the correct answer is $\frac{80}{9}$.
Candidates can download this ebook to know all about SSC CGL.
Admit Card | Eligibility | Application | Selection Process | Preparation Tips | Result | Answer Key
Question : A can finish a work in 20 days and B can complete the same work in 15 days. B worked for 9 days and left the job. In how many days can A alone finish the remaining work?
Question : P, Q, and R can complete a piece of work in 10 days, 15 days, and 20 days, respectively. If they work together, in how many days can they finish the same work?
Question : A and B together can finish a work in 30 days. They worked on it for 20 days and then B left. The remaining work was done by A alone in 20 days. In how many days can A alone finish the work?
Question : A, B, and C can do a job in 6 days, 12 days and 15 days respectively. After $\frac{1}{8}$th of the work is completed, C leaves the job. The rest of the work is done by A and B together. The time taken to finish the work is:
Question : To do certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in _______ days.