Question : A and B are equally efficient, and each can individually complete a piece of work in 36 days if none takes any holiday. A and B started working together on this piece of work, but A took a day off after every five days of work, while B took a day off after every seven days of work. If the duo had started work on 1 July 2021, on which date was the work completed?
Option 1: 22 July 2021
Option 2: 19 July 2021
Option 3: 21 July 2021
Option 4: 20 July 2021
Correct Answer: 21 July 2021
Solution : Given, A and B can individually complete a piece of work in 36 days ⇒ Efficiency of A and B = $\frac{1}{36}$ They started working on 1 July 2021. A took a day off after every five days of work and B took a day off after every seven days of work. For 5 days, A and B work together. ⇒ Till 6 July 2021, $\frac{10}{36}$ of the work will be completed On the 7th day, 7 July 2021, only B worked ⇒ $\frac{10}{36}+\frac{1}{36}$ of the work will be completed. ⇒ $\frac{11}{36}$ of the work will be completed by 7 July 2021. Again on the 7th day, 8 July 2021, both of them worked together ⇒ $\frac{13}{36}$ of the work will be completed till 8 July, 2021. Now B is on leave and A alone works. ⇒ $\frac{14}{36}$ of the work will be completed till 9 July, 2021 Now, again both of them will work together for 5 days. ⇒ $\frac{14}{36}+\frac{10}{36}$ ⇒ $\frac{24}{36}$ of the work will be completed till 14 July, 2021. Now, A is going on leave. ⇒ $\frac{25}{36}$ of the work will be completed by 15 July 2021. Now, for 1 day, A and B again work together. ⇒ $\frac{27}{36}$ of the work will be completed till 16 July, 2021. Now, B is going on leave and A works alone. ⇒ $\frac{28}{36}$ of the work will be done by 17 July 2021. Now they work together for 5 days, but they have to work for 4 more days to complete the work ⇒ $\frac{28}{36}+\frac{8}{36}$ ⇒ $\frac{36}{36}$ i.e., full work will be completed by 21 July 2021. Hence, the correct answer is 21 July 2021.
Result | Eligibility | Application | Selection Process | Cutoff | Admit Card | Preparation Tips
Question : A, B and C can do a piece of work in 20 days, 30 days and 60 days respectively. If A works daily and on every third day B and C also work with A, then in how many days, will the work be completed?
Question : A group of workers can complete a piece of work in 50 days when they are working individually. On the first day one person works, on the second day, another person joins him, on the third day one more person joins them and this process continues till the work is completed. How
Question : A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively. How soon can the work be done if A works with B on the first day, A works with C on the second day and so on?
Question : A, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed?
Question : John can do a piece of work alone in 20 days, while Ravi can do the same piece of work alone in 28 days. In how many days can the duo complete the same work if they work together?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile