Question : A and B can complete a work in 10 and 16 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in:
Option 1: $12 \frac{1}{4}$ days
Option 2: $13 \frac{1}{4}$ days
Option 3: $15 \frac{1}{4}$ days
Option 4: $14 \frac{1}{4}$ days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
Correct Answer: $12 \frac{1}{4}$ days
Solution :
Given, A and B can complete a piece of work in 10 and 16 days, respectively.
Work done by A in a day = $\frac{1}{10}$
Work done by B in a day = $\frac{1}{16}$
⇒ Work done by A and B in 2 days if they work alternatively = $\frac{1}{10}+\frac{1}{16}=\frac{13}{80}$
⇒ Work done by A and B in 12 days if they work alternatively = $\frac{13}{80}×6=\frac{39}{40}$
⇒ Work left after 12 days = $1-\frac{39}{40}=\frac{1}{40}$
⇒ Time taken by A to complete remaining work = $\frac{\frac{1}{40}}{\frac{1}{10}}=\frac{1}{4}$ days
$\therefore$ Total time = $12+\frac{1}{4}=12\frac{1}{4}$ days
Hence, the correct answer is $12\frac{1}{4}$ days.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.