Question : A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. The time taken by A, B and C together to do the job is:

Option 1: 4 days

Option 2: 9 days

Option 3: 8 days

Option 4: 5 days


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 8 days


Solution : Given: A and B can do a piece of work in 15 days. B and C can do the same work in 10 days also A and C can do the same in 12 days.
(A + B) in 1 day can do $\frac{1}{15}$ part of the work
(B + C) in 1 day can do $\frac{1}{10}$ part of the work
(C + A) in 1 day can do $\frac{1}{12}$ part of the work
So, the part of the work (A + B + C) can be done in 1 day,
= $\frac{1}{2}(\frac{1}{15}+\frac{1}{10}+\frac{1}{12})$
= $\frac{1}{2}(\frac{4+6+5}{60})$ = $\frac{15}{120}$
Therefore, the time taken by A, B, and C together to do the job is $(\frac{1}{\frac{15}{120}})=\frac{120}{15}$ = 8 days
Hence, the correct answer is 8 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books