Question : A and B can finish a work in 10 days, B and C can finish it in 12 days and C and A can finish in 6 days. In how many days A alone can finish the work?
Option 1: $\frac{120}{9}$
Option 2: $12$
Option 3: $\frac{120}{11}$
Option 4: $\frac{121}{12}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{120}{11}$
Solution : Time taken by A and B to do the work = 10 days Let the work done by A, B, and C in a day be a, b and c units, respectively. Work done by A and B together in a day = $\frac{1}{10}$ ⇒ a + b = $\frac{1}{10}$ ------------(i) Time taken by B and C to do the work = 12 days Work done by B and C together in a day = $\frac{1}{12}$ ⇒ b + c = $\frac{1}{12}$ ------------(ii) Time taken by C and A to do the work = 6 days Work done by C and A together in a day = $\frac{1}{6}$ ⇒ c + a = $\frac{1}{6}$ ------------(iii) Subtracting (ii) from (i), ⇒ a – c = $\frac{1}{10}$-$\frac{1}{12}$ = $\frac{2}{120}$ ⇒ a – c = $\frac{1}{60}$ -------------(iv) Adding equations (iii) and (iv), ⇒ 2a = $\frac{1}{6}$+$\frac{1}{60}$ = $\frac{11}{60}$ $\therefore$ a = $\frac{11}{120}$ Work done by A alone in a day = $\frac{11}{120}$ $\therefore$ Time taken by A alone to do the work = $\frac{120}{11}$ days Hence, the correct answer is $\frac{120}{11}$.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B, and C finish it, working all together?
Question : 10 women can do a work in 6 days and 6 men can do the same work in 5 days. If all these men and women work together, then how many days will they take to finish this work?
Question : A alone can do a work in 11 days. B alone can do the same work in 22 days. C alone can do the same work in 33 days. They work in the following manner: Day 1: A and B work. Day 2: B and C work. Day 3: C and A work. Day 4: A and B work. And so on.
Question : A can do a piece of work in 20 days and B in 15 days. With the help of C, they finish the work in 5 days. C can alone do the work in:
Question : A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile