Question : A and B together can complete a given work in 10 days. C can complete the same work alone in 15 days. In how many days can they complete the work, if all three work together?
Option 1: 8 days
Option 2: 5 days
Option 3: 6 days
Option 4: 10 days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 6 days
Solution : 1 day's work of A and B = $\frac{1}{10}$ 1 day's work of C = $\frac{1}{15}$ 1 day's work of A, B and C together = $\frac{1}{10}+\frac{1}{15} = \frac{3+2}{30} = \frac{1}{6}$ Thus, the work is completed in 6 days. Hence, the correct answer is 6 days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : A, B, and C together can complete a work in 5 days. A and B together can complete the same work in 6 days. C alone can finish the same work in how many days?
Question : Rohan alone can do a work in 10 days and Mohan alone can do the same work in 15 days. In how many days will they together complete the same work?
Question : A and B together complete a work in 20 days, B and C together complete the same work in 30 days, and C and A together complete the same work in 24 days. In how many days A, B, and C together can complete the same work?
Question : Seema alone can do a piece of work in 8 days and her sister Reema alone can do the same work in 24 days. If they worked together, then in how many days they will complete the work?
Question : B and C can complete work alone in 10 days and 30 days respectively. They began the work together but B left the work after some days and C completed the remaining work in 10 days. After how many days from the beginning B left the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile