4 Views

Question : A and B together can complete a project in 10 days. They started together, but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?

Option 1: 15 days

Option 2: 20 days

Option 3: 30 days

Option 4: 45 days


Team Careers360 4th Jan, 2024
Answer (1)
Team Careers360 12th Jan, 2024

Correct Answer: 30 days


Solution : Given: A and B together can complete a project in 10 days.
Let the efficiency of A is $x$ and B is $y$ respectively.
Total work = Efficiency × Time
Total work is $(x+y)×10 = 10(x+y)$
They started together, but A left after 2 days and the remaining work was completed by B in 12 days.
$(x+y)×2 + y×12 = 10(x+y)$
⇒ $2x+2y+12y = 10x+10y$
⇒ $8x = 4y$
⇒ $\frac{x}{y} = \frac{4}{8} = \frac{1}{2}$
Then, the efficiency of A is 1 unit and the efficiency of B is 2 units.
Total work is $10(x+y) = 10(1+2) = 30$ units
Time taken by A to complete the whole work is $\frac{30}{1}$ = 30 days
Hence, the correct answer is 30 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books