Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Option 1: 8 days
Option 2: 10 days
Option 3: 15 days
Option 4: 12 days
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: 12 days
Solution :
Given,
A and B together can complete a work in 20 days
⇒ Work done by A and B together in 1 day = $\frac{1}{20}$
Also, B and C together can complete the same work in 15 days
⇒ Work done by B and C together in 1 day = $\frac{1}{15}$
A, B, and C all work together and the same work gets completed in 10 days
⇒ Work done by A, B, and C together in 1 day = $\frac{1}{10}$
For one day,
⇒ Work done by C + Work done by A and B together = $\frac{1}{10}$
⇒ Work done by C + $\frac{1}{20}=\frac{1}{10}$
⇒ Work done by C = $\frac{1}{10}-\frac{1}{20}$ = $\frac{1}{20}$
And, Work done by A + Work done by B and C together = $\frac{1}{10}$
⇒ Work done by A + $\frac{1}{15}=\frac{1}{10}$
⇒ Work done by A = $\frac{1}{10}-\frac{1}{15}$
⇒ Work done by A = $\frac{3-2}{30}$
⇒ Work done by A = $\frac{1}{30}$
$\therefore$ Work done by A and C in one day together = $\frac{1}{20}+\frac{1}{30}=\frac{3+2}{60}=\frac{1}{12}$
⇒ They will take 12 days to complete the work.
Hence, the correct answer is 12 days.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.