Question : A and B together can finish a job in 24 days, while A, B, and C together can finish the same job in 8 days. C alone will finish the job in:
Option 1: 12 days
Option 2: 14 days
Option 3: 16 days
Option 4: 24 days
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 12 days
Solution : Given: A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. Then in 1 day A and B together can finish $\frac{1}{24}$th part of the job. Also, A, B, and C together can finish the same job in 8 days. ⇒ In 1 day A, B, and C together can finish $\frac{1}{8}$ part of the job. Then C alone in 1 day can finish $(\frac{1}{8}-\frac{1}{24}) = (\frac{3-1}{24}) = \frac{2}{24}$th part of the job $\therefore$ C alone will finish the job in $=\frac{1}{\frac{2}{24}} = \frac{24}{2}=12$ days Hence, the correct answer is 12 days.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A and B can do a work in 8 days and B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in:
Question : A and B together can do a piece of work in 36 days and B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in:
Question : A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A, B, and C complete it in 6 days. Find the number of days required to finish the work by A and C is:
Question : A, B and C together can complete a work in 12 days. A and B alone can do the same work in 36 days. In how many days can C alone complete the same work?
Question : A, B, and C can do a job working alone in 50, 75 and 20 days, respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?