A and B together do a work in 6 days.A alone do it in 9 days?How many days taken by B to conplete the same work alone?
Hi Sagar,
Please use this platform to ask questions related to information about various entrance examinations, colleges or universities, etc in the future.
Now to answer your question,
In 6 days, A and B both complete a work.
In 1 day, they both do 1/6 work.
In 9 days A does a work.
In 1 day, A does 1/9 work.
Therefore, in one day B does (1/6-1/9) work, i.e. 1/18 work.
Thus, B will take 36 days to complete the same work.
BEST WISHES!