Question : A and B undertake a piece of work for Rs. 250. A alone can do that work in 5 days and B alone can do that work in 15 days. With the help of C, they finish the work in 3 days. If everyone gets paid in proportion to the work done by them, the amount C will get is:
Option 1: Rs. 50
Option 2: Rs. 100
Option 3: Rs. 150
Option 4: Rs. 200
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: Rs. 50
Solution : Given: A and B undertake a piece of work for Rs. 250. A's 1 day's work = $\frac{1}{5}$ B's 1 day's work = $\frac{1}{15}$ (A + B + C)'s 1 day's work = $\frac{1}{3}$ So, C's 1 day's work = $\frac{1}{3}-(\frac{1}{5}+\frac{1}{15})=\frac{1}{3}-\frac{4}{15}=\frac{1}{15}$ The ratio of efficiencies by A, B, C is $\frac{1}{5}:\frac{1}{15}:\frac{1}{15}=3:1:1$ So, C's amount $=\frac{1}{3+1+1}×250=50$ Hence, the correct answer is Rs. 50.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A can do a piece of work in 20 days and B in 15 days. With the help of C, they finish the work in 5 days. C can alone do the work in:
Question : A, B, and C are employed to do a piece of work for Rs. 575. A and C are supposed to finish $\frac{19}{23}$th of the work together. The amount shall be paid to B is:
Question : Three persons undertake to complete a piece of work for Rs. 1,200. The first person can complete the work in 8 days, the second person in 12 days and the third person in 16 days. They complete the work with the help of a fourth person in three days. What does the fourth
Question : A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone?
Question : A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the job. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile