Question : A and B were assigned to do a job for Rs. 1,200. Working alone, A can do it in 15 days and B, in 12 days. With the help of C, they can finish in 5 days. The share of the amount that C earns is:
Option 1: Rs. 300
Option 2: Rs. 400
Option 3: Rs. 500
Option 4: Rs. 600
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: Rs. 300
Solution : The time taken by A alone = 15 days ⇒ Part of the work done by A in 1 day = $\frac{1}{15}$ The time taken by B alone = 12 days ⇒ Part of the work done by B in 1 day = $\frac{1}{12}$ Let the time taken by C alone = $x$ ⇒ Part of the work done by C in 1 day = $\frac{1}{x}$ The time taken by A, B, and C = 5 days ⇒ Part of the work done by A, B, and C together in 1 day = $\frac{1}{5}$ According to the question, $\frac{1}{5}=\frac{1}{15}+\frac{1}{12}+\frac{1}{x}$ ⇒ $\frac{1}{x}=\frac{1}{5}-\frac{1}{12}-\frac{1}{15}=\frac{12 – 5 – 4}{60} = \frac{1}{20}$ The ratio of the amounts A, B, and C earn $= \frac{1}{15} : \frac{1}{12} :\frac{1}{20} = 4: 5: 3$ Since total amount = 1200, Share of the amount earned by C = $\frac{3}{12}× 1200$ = Rs. $300$ Hence, the correct answer is Rs. 300.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Mohit and Rohit undertook a work for Rs. 2200. Mohit alone can do that work in 10 days and Rohit alone can do the same work in 12 days. If they work together, then what will be the difference in the amount they receive?
Question : K1 can do a piece of work alone in 4 days, K2 can do the same work alone in 8 days, while K3 can do it alone in 32 days. They work together to complete the work and receive a total of Rs. 3,900 as payment for doing the work. What is the share of
Question : A alone can do a work in 25 days and B alone can do the same work in 40 days. They worked together and were paid a total of Rs. 5200. What is the difference between their shares?
Question : P alone can do work in 10 days, Q alone can do the same work in 15 days and R alone can do the same work in 12 days. They jointly complete the work and earn Rs. 3000. What is the share of R?
Question : Stanie and Paul accept a piece of work for Rs. 28,800. Working alone, one could do it in 36 days and the other, in 48 days. With the assistance of an expert, they finish it in 12 days. How much remuneration should the expert get?