Question : A and B working separately can do a piece of work in 9 and 15 days respectively. If they work on alternate days, starting with A, then the work will be completed in:
Option 1: 10 days
Option 2: 11 days
Option 3: 9 days
Option 4: 12 days
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: 11 days
Solution :
Given: A and B working separately can do a piece of work in 9 and 15 days respectively. They work on alternate days, starting with A.
Let the total work = LCM of 9 and 15 = 45 units
A’s 1 day work = $\frac{45}{9}$ = 5 units
B’s 1 day work = $\frac{45}{15}$ = 3 units
If they work on alternate days, they will finish (5 + 3) = 8 units of work in 2 days,
In 10 days they will finish (8 × 5) = 40 units of work,
The remaining work = (45 – 40) = 5 units of work, which A can finish on the 11th day.
So, the work will be completed in 11 days.
Hence, the correct answer is 11 days.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.