Question : A, B, and C are employed to do a piece of work for INR 5,290. A and B together are supposed to do $\frac{19}{23}$ of the work and B and C together $\frac{8}{23}$ of the work. Then A should be paid:
Option 1: INR 4,250
Option 2: INR 3,450
Option 3: INR 1,950
Option 4: INR 2,290
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: INR 3,450
Solution : Part of work done by A and B together = $\frac{19}{23}$ of total work Part of work done by B and C together = $\frac{8}{23}$ of total work Part of the work done by A alone = Total work – Part of work done by B and C together = (1 – $\frac{8}{23}$ ) of total work = $\frac{15}{23}$ of total work Total wages = INR 5,290 So, the wage of A = $\frac{15}{23}$ × 5290 = INR 3,450 Hence, the correct answer is INR 3,450.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A, B, and C are employed to do a piece of work for Rs. 575. A and C are supposed to finish $\frac{19}{23}$th of the work together. The amount shall be paid to B is:
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : A and B can do a piece of work in 5 days and 10 days, respectively. They began the work together but A left after some days and B finished the remaining work in 8 days. After how many days did A leave?
Question : A and B together can do a piece of work in 36 days and B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in:
Question : A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile