Question : A, B, and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work is:
Option 1: $8\frac{2}{3}$
Option 2: $6\frac{2}{3}$
Option 3: $7$
Option 4: $6$
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: $7$
Solution :
Given: A, B, and C can complete a work in 10, 12, and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left.
Let total work = LCM of 10, 12, and 15 = 60 units [Use: Efficiency = $\frac{\text{Total Work}}{\text{Time}}$]
So, A's efficiency = $\frac{60}{10}=6$
B's efficiency is = $\frac{60}{12}=5$
C's efficiency is = $\frac{60}{15}=4$
Let $n$ number of days required to complete the 60 units of work.
According to the question,
$6 \times(n-5) + 5 \times (n-3) + 4 n = 60$
⇒ $6n-30+5n-15+4n=60$
⇒ $15n = 105$
⇒ $n=7$
Hence, the correct answer is $7$.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.