Question : A, B, and C can complete a work in 10, 12, and 15 days respectively. They started the work together, but A left the work before five days of its completion. B also left the job two days after A left. In how many days was the work completed?

Option 1: 4 days

Option 2: 5 days

Option 3: 7 days

Option 4: 8 days


Team Careers360 9th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 7 days


Solution : A left the work 5 days before completion.
B left the work 3 days before completion.
We know that Total work = Number of days × Efficiency of work.
Let the number of days required to complete the whole work = $x$ and the whole work is 1.
1 day work of A = $\frac{1}{10}$
1 day work of B = $\frac{1}{12}$
1 day work of C = $\frac{1}{15}$
According to the question,
$\frac{x-5}{10} + \frac{x-3}{12} + \frac{x}{15} = 1$
$⇒6(x-5)+5(x-3)+4x = 60$
$⇒6x-30+5x-15+4x =60$
$⇒15x-45 = 60$
$⇒15x=105$
$\therefore x=7$
Hence, the correct answer is 7 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books