2 Views

Question : A, B, and C can do a job working alone in 50, 75 and 20 days, respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

Option 1: 20

Option 2: 30

Option 3: 18

Option 4: 24


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 16th Jan, 2024

Correct Answer: 20


Solution : Given:
A, B, and C can do a job working alone for 50, 75 and 20 days, respectively.
Total work = LCM of (50, 75, 20) = 300 units
Efficiency of A = $\frac{300}{50}=6$
Efficiency of B = $\frac{300}{75}=4$
Efficiency of C = $\frac{300}{20}=15$
Total work they have done in the first 4 days.
= 4 × (6 + 4 + 15) = 100 units
Remaining work = 300 – 100 = 200 units
Therefore, days required for A & B to complete the work
= $\frac{\text{Remaining work}}{\text{Efficiency of A and B combined}}$
= $\frac{200}{6+4}$
= $20$ days
Hence, the correct answer is 20.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books