Question : A, B and C together can complete a work in 12 days. A and B alone can do the same work in 36 days. In how many days can C alone complete the same work?
Option 1: 48
Option 2: 25
Option 3: 12
Option 4: 36
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 36
Solution : Given: A and B alone can do the same work in 36 days. Let the total work = LCM of (12, 36, 36) = 36 units Efficiency of A $=\frac{36}{36} = 1$ unit per day Efficiency of B $=\frac{36}{36} = 1$ unit per day Efficiency of A, B, and C together $\frac{36}{12} = 3$ units per day Now, the efficiency of C = 3 – 1 – 1 = 1 unit per day Then, the time C takes to complete the whole task alone is $\frac{36}{1} = 36$ days Hence, the correct answer is 36.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A and B can do a work in $26 \frac{2}{3}$ days. B and C together can complete the same work in 48 days, while A and C together can complete the same work in 30 days. How long (in days) will A alone take to complete 60% of the work?
Question : A alone can do a work in 11 days. B alone can do the same work in 22 days. C alone can do the same work in 33 days. They work in the following manner: Day 1: A and B work. Day 2: B and C work. Day 3: C and A work. Day 4: A and B work. And so on.
Question : A and B together can do a piece of work in 12 days. A alone can do it in 18 days. In how many days B alone can do the work?
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : If A and B together can do a piece of work in 20 days, and A alone can do the same work in 30 days, in how many days can B alone complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile