Question : A, B, and C together can finish a piece of work in 20 days. A alone can finish the work in 40 days. What part of the work B and C together can finish in a day?
Option 1: $\frac{1}{5}$
Option 2: $\frac{1}{20}$
Option 3: $\frac{1}{10}$
Option 4: $\frac{1}{40}$
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{1}{40}$
Solution : A, B, and C per day work = $\frac{1}{20}$ A's working rate per day = $\frac{1}{40}$ The work rate of B and C together = $\frac{1}{20} - \frac{1}{40}$ = $\frac{1}{40}$ Hence, the correct answer is $\frac{1}{40}$.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A can finish a work in 15 days, B can finish the same work in 25 days. They work together for 5 days. The rest of the work is finished by A and C in 4 days. Then C alone can finish the work in:
Question : Rahul alone can complete a work in 10 days and Sonu alone can complete the same work in 15 days. If they work together for 4 days, then what part of total work is left?
Question : A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?
Question : Three people A, B, and C worked together and finished a work in 9 days. If A alone can finish the same work in 18 days, and B alone in 30 days, then the number of days C alone will take is:
Question : A and B can finish a work together in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days can A alone finish the job?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile