Question : A can complete 25% of a work in 10 days. B can complete 40% of the same work in 16 days. In how many days will A and B together complete twice the work mentioned above?

Option 1: 20

Option 2: 40

Option 3: 60

Option 4: 50


Team Careers360 23rd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 40


Solution : Time taken by A to complete 25% of a work = 10 days
Time taken by A to complete the work = $10×\frac{100}{25}$ = 40 days
Part of work done by A in a day = $\frac{1}{40}$
Time taken by B to complete 40% of the same work = 16 days
Time taken by B to complete the same work = $16×\frac{100}{40}$ = 40 days
Part of work done by B in a day = $\frac{1}{40}$
Part of work done by A and B in a day = $\frac{1}{40}+\frac{1}{40}$ = $\frac{2}{40}$ = $\frac{1}{20}$
Time taken by A and B to complete the work = 20 days
Time taken by A and B to complete twice the work = 2 × 20 = 40 days
Hence, the correct answer is 40 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books