Solution :
One day's work of A = $\frac{1}{120}$
One day's work of A and B together = $\frac{1}{72}$
Let B alone complete the work in b days.
One day's work of B = $\frac{1}{b}$
$\frac{1}{120}+\frac{1}{b}=\frac{1}{72}$
⇒ $\frac{1}{b}=\frac{1}{72} -\frac{1}{120}$
⇒ $\frac{1}{b}=\frac{15-9}{1080}$
⇒ $\frac{1}{b}=\frac{1}{180}$
⇒ $\therefore b=180$ days
Hence, the correct answer is 180.
Related Questions
Know More about
Staff Selection Commission Combined Grad ...
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Get Updates BrochureYour Staff Selection Commission Combined Graduate Level Exam brochure has been successfully mailed to your registered email id “”.