Question : A can complete a piece of work alone in 120 days, while A and B, working together, can complete the same work in 72 days. In how many days can B, working alone, complete this piece of work?

Option 1: 180

Option 2: 200

Option 3: 160

Option 4: 216


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 180


Solution : One day's work of A = $\frac{1}{120}$
One day's work of A and B together = $\frac{1}{72}$
Let B alone complete the work in b days.
One day's work of B = $\frac{1}{b}$
$\frac{1}{120}+\frac{1}{b}=\frac{1}{72}$
⇒ $\frac{1}{b}=\frac{1}{72} -\frac{1}{120}$
⇒ $\frac{1}{b}=\frac{15-9}{1080}$
⇒ $\frac{1}{b}=\frac{1}{180}$
⇒ $\therefore b=180$ days
Hence, the correct answer is 180.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books