Question : A can complete a piece of work alone in 120 days, while A and B, working together, can complete the same work in 72 days. In how many days can B, working alone, complete this piece of work?
Option 1: 180
Option 2: 200
Option 3: 160
Option 4: 216
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 180
Solution : One day's work of A = $\frac{1}{120}$ One day's work of A and B together = $\frac{1}{72}$ Let B alone complete the work in b days. One day's work of B = $\frac{1}{b}$ $\frac{1}{120}+\frac{1}{b}=\frac{1}{72}$ ⇒ $\frac{1}{b}=\frac{1}{72} -\frac{1}{120}$ ⇒ $\frac{1}{b}=\frac{15-9}{1080}$ ⇒ $\frac{1}{b}=\frac{1}{180}$ ⇒ $\therefore b=180$ days Hence, the correct answer is 180.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : If A and B together can do a piece of work in 20 days, and A alone can do the same work in 30 days, in how many days can B alone complete the same work?
Question : A and B together can do a piece of work in 12 days, while A alone can do the same work in 30 days. B alone can do it in:
Question : A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They started the work together and completed the work such that B was not working in the last 2 days and A did not work in the last 3 days. In how many days
Question : A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A single person can complete the work in:
Question : Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do it in 7 days, how long would Rajat take to complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile