Question : A can complete a piece of work in 9 days. B and C can complete the same work in 12 days and 18 days respectively. If A, B, and C work together, then in how many days will they complete the work?

Option 1: 10 days

Option 2: 8 days

Option 3: 4 days

Option 4: 15 days


Team Careers360 24th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 4 days


Solution : 1 day's work of A = $\frac{1}{9}$
1 day's work of B = $\frac{1}{12}$
1 day's work of A = $\frac{1}{18}$
1 day's work of (A + B + C) $=\frac{1}{9}+\frac{1}{12}+\frac{1}{18}=\frac{4+3+2}{36}=\frac{9}{36}$
$\therefore$ So they can complete the whole work in $\frac{36}{9}$ = 4 days
Hence, the correct answer is 4 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books