Question : A can complete a task in 25 days while B can complete the same task in 30 days. They work on alternate days, starting with A. Both A and B follow this pattern for 5 days and then, A leaves. In how many days will B finish the remaining work?

Option 1: $24 \frac{2}{5}$

Option 2: $5 \frac{2}{5}$

Option 3: $5 \frac{3}{5}$

Option 4: $24 \frac{3}{5}$


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $24 \frac{2}{5}$


Solution : A can complete the task in 25 days.
Work done by A in one day = $\frac{1}{25}$
B can complete the task in 30 days.
Work done by B in one day = $\frac{1}{30}$
They work on alternate days for 5 days.
In 5 days, A worked for 3 days and B worked for 2 days.
Work done in 5 days = $\frac{3}{25} + \frac{2}{30} = \frac{28}{150}$
After 5 days, A leaves, and B continues.
The remaining work = $ 1 - \frac{28}{150} = \frac{122}{150}$
If B can do $\frac{1}{30}$ work in one day, the number of days B needs to complete the work = $\frac{\frac{122}{150}}{\frac{1}{30}} =24\frac{2}{5}$ days
Hence, the correct answer is $24 \frac{2}{5}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books