2 Views

Question : A can complete a work in 8 days and B can complete the same work in 11 days. How many days will they take, if both work together?

Option 1: $4 \frac{12}{17}$

Option 2: $5 \frac{12}{19}$

Option 3: $4 \frac{11}{19}$

Option 4: $4 \frac{12}{19}$


Team Careers360 15th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: $4 \frac{12}{19}$


Solution : The rate at which A works is $\frac{1}{8}$ work per day and the rate at which B works is $\frac{1}{11}$ work per day.
Together, A and B can do $\frac{1}{8} + \frac{1}{11} = \frac{19}{88}$ work per day.
So, the time taken to complete the work when A and B work together is the reciprocal of their combined work rate = $\frac{88}{19} = 4 \frac{12}{19}$ days
Hence, the correct answer is $4 \frac{12}{19}$.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books