Question : A can do a piece of work alone in 40 days. A and B together can do the same work in 10 days. C is 50% less efficient than B. In how many days can A and C together complete the same work?
Option 1: 20 days
Option 2: 24 days
Option 3: 16 days
Option 4: 12 days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 16 days
Solution : According to the question (A + B)'s 1 day work = $\frac{1}{10}$ A's 1 day work = $\frac{1}{40}$ ⇒ B's 1 day work = $\frac{1}{10}$ – $\frac{1}{40}$ = $\frac{3}{40}$ Now, C's 1 day work = $\frac{1}{2}$ of B's 1 day work = $\frac{3}{80}$ ⇒ (A + C)'s 1 day work = $\frac{1}{40}$ + $\frac{3}{80}$ = $\frac{5}{80}$ ⇒ Time taken by A and C together = $\frac{1}{Rate}$ = $\frac{1}{\frac{5}{80}}$ = $\frac{80}{5}$ = 16 Hence, the correct answer is 16 days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : A and B together complete a work in 20 days, B and C together complete the same work in 30 days, and C and A together complete the same work in 24 days. In how many days A, B, and C together can complete the same work?
Question : A and B together can do a piece of work in 24 days. A alone can do this work in 40 days. In how many days can B alone do this work?
Question : A, B, and C together can do a piece of work in 6 days. A and B together can do the same work in 12 days. B alone can do the same work in 18 days. In how many days can A and C together do the same work?
Question : Sachin is 12.5 percent less efficient than Rohit. If Sachin alone can finish a work in 24 days, then in how many days will Rohit alone finish the same work?
Question : A, B, and C together can complete a work in 5 days. A and B together can complete the same work in 6 days. C alone can finish the same work in how many days?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile