Question : A can do a piece of work in 12 days and B can do the same work in 15 days. If both do the work together, then in how many days will the work be completed?
Option 1: $7 \frac{2}{3}$
Option 2: $6 \frac{2}{3}$
Option 3: $5 \frac{2}{3}$
Option 4: $8 \frac{2}{3}$
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $6 \frac{2}{3}$
Solution : Given, A can do a piece of work in 12 days and B can do the same work in 15 days. Let the total work be 1 unit. Amount of work done by A in 1 day = $\frac{1}{12}$ Amount of work done by B in 1 day = $\frac{1}{15}$ Amount of work done by A and B together in 1 day = $\frac{1}{12}+\frac{1}{15}=\frac{3}{20}$ So, time taken by them to complete the whole work = $\frac{20}{3}$ = $6\frac{2}{3}$ days Hence, the correct answer is $6\frac{2}{3}$.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A can do a piece of work in 24 days and B can do the same work in 30 days. If they work on it together for 8 days, then the fraction of the work that is left is:
Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Question : X can do a piece of work in 14 days, Y can do the same work in 28 days and Z can do it in 42 days. In how many days can X, Y, and Z together complete the work?
Question : A can finish a work in 7 days. B can finish the same work in 9 days. The number of days required to finish the same work by both of them together is:
Question : A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?