Question : A can do a piece of work in 30 days while B can do it in 40 days. How many days can A and B when working together do it?

Option 1: $42\frac{3}{4}$ days

Option 2: $27\frac{1}{7}$ days

Option 3: $17\frac{1}{7}$ days

Option 4: $70$ days


Team Careers360 7th Jan, 2024
Answer (1)
Team Careers360 17th Jan, 2024

Correct Answer: $17\frac{1}{7}$ days


Solution : Given:
A can do a piece of work in 30 days while B can do it in 40 days.
(A + B)'s work in 1 day $=\frac{1}{30} + \frac{1}{40}=\frac{4+3}{120} = \frac{7}{120}$
$\therefore$ (A + B) can complete the work in $=\frac{120}{7} = 17\frac{1}{7}$ days
Hence, the correct answer is $17\frac{1}{7}$days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books