4 Views

Question : A can do a piece of work in 5 days and B in 4 days. How long will they take to do the same work when working together?

Option 1: $9$ days

Option 2: $2\frac{2}{9}$ days

Option 3: $4\frac{1}{3}$ days

Option 4: $3\frac{2}{9}$ days


Team Careers360 22nd Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: $2\frac{2}{9}$ days


Solution : Given: A can do a piece of work in 5 days and B in 4 days.
If a man can do the work in $n$ days, then one day's work of the man $=\frac{1}{n}$.
1 day work of A $=\frac{1}{5}$
1 day work of B $=\frac{1}{4}$
1 day work of (A + B) together $=\frac{1}{5} + \frac{1}{4}=\frac{4+5}{20} = \frac{9}{20}$
So, (A + B) together can complete the work in $=\frac{20}{9} = 2\frac{2}{9}$ days
Hence, the correct answer is $2\frac{2}{9}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books