14 Views

Question : A can do a piece of work in 6 days, working 8 hours a day, while B can do the same work in 4 days, working 10 hours a day. If the work has to be completed in 5 days, how many hours do they need to work together in a day?

Option 1: $4$

Option 2: $5\frac{4}{11}$

Option 3: $6\frac{4}{11}$

Option 4: $4\frac{4}{11}$


Team Careers360 3rd Jan, 2024
Answer (1)
Team Careers360 14th Jan, 2024

Correct Answer: $4\frac{4}{11}$


Solution : Part of the work A completes in an hour in a single day $\frac{1}{6}\times\frac{1}{8}=\frac{1}{48}$
Part of the work B completes in an hour in a single day $\frac{1}{4}\times\frac{1}{10}=\frac{1}{40}$
Let the number of hours needed to work together in a day be $y$.
According to the question,
$5y \times(\frac{1}{48}+\frac{1}{40})=1$
⇒ $y = \frac{40 \times48}{88 \times 5}$
⇒ $y = \frac{48}{11} =4\frac{4}{11}$ hours
Hence, the correct answer is $4\frac{4}{11}$ hours.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books